Adarsh Tropica – Phase II

Sarjapur Road · by Adarsh Developers

Price not published

Sarjapur RoadPictures coming soon

From Adarsh Developers’ website, 7 Oct ·

From
Not published Ask Adarsh Developers
Move-in
K-RERA completion Jul 2029builder's date not published
Is it on schedule?
Behind time

Built13%

Time gone37%

K-RERA
Two registrationsFound on the register, 7 Oct 2026Look it up on K-RERA (opens in a new tab)
Where these facts come from
  • Keys K-RERA · 7 Oct
  • Built K-RERA · 7 Oct
  • K-RERA Register check · 7 Oct

Information from Adarsh Developers’ website, 7 Oct 2026, for internal review

Facts at a glance

As published by K-RERA and by Adarsh Developers, each with where it comes from. We don't rate homes.

K-RERA registrations
PRM/KA/RERA/1251/446/PR/111022/005309RegisteredLook it up on K-RERA (opens in a new tab)PRM/KA/RERA/1251/446/PR/010325/007535RegisteredLook it up on K-RERA (opens in a new tab)K-RERA register · 7 Oct
Completion, per K-RERA
Jul 2029K-RERA · 7 Oct
Registered on K-RERA
11 Oct 2022K-RERA · 7 Oct
Towers
8K-RERA · 7 Oct
Homes registered
1,003K-RERA · 7 Oct
Homes on offer
2.5 & 3 BHKAdarsh Developers’ website · 7 Oct

What will we pay, all-in?

Not published Not published

Ask Adarsh Developers for the price. Ask Adarsh Developers

Where this comes fromNot published · ask Adarsh Developers

What Adarsh Developers has published, what the government will charge, and the charges still to come, shown empty so nothing arrives later as a surprise.

All-inNot published Adarsh Developers hasn't published a dated sample cost sheet, so there is no all-in to show. We don't add one up from the parts we know. Ask Adarsh Developers for one home's sheet

The cost, line by line
LineSourceAmount
Agreement value
Price of the homeThe phase's lowest published price, before charges. It isn't tied to one plan.Ask Adarsh DevelopersNot published
Floor riseAsk Adarsh DevelopersNot published
Preferred locationAsk Adarsh DevelopersNot published
Covered car parkAsk Adarsh DevelopersNot published
Club, BESCOM and BWSSB deposits, legalAsk Adarsh DevelopersNot published
Government
GST, 5%While it is being built. Nil once the occupancy certificate is issued.Statutory · at the state's rates · 7 OctNot published
Stamp duty, about 5.6%5% duty, plus a 10% cess and a 2% surcharge on the duty, on the agreement value or the guidance value, whichever is higher.Estimate · at the state's rates · 7 OctNot published
Registration, 2%Since 31 Aug 2025.Statutory · at the state's rates · 7 OctNot published
At handover
Maintenance in advanceAsk Adarsh DevelopersNot published
Corpus fundAsk Adarsh DevelopersNot published

The government lines are Clikin.ai's estimates at the state's rates, read 7 Oct 2026. The amounts are worked on the published price only, so they rise with the charges still to come. TDS of 1% is deducted from what you pay, not added to it.

Per square foot

Not worked out yet. The starting price isn't tied to one plan, so dividing would mislead. It will be, once a dated cost sheet names the home.

When you pay

Before the agreement: at most 10% of the cost, by law (RERA Act, s.13).

Adarsh Developers’ payment plan: not published.

RERA Act 2016, s.13 · 7 Oct

Need the exact figure?

Ask Adarsh Developers for this home's full cost sheet. It comes back in writing, dated.

Ask for this home's sheet

The sample cost sheet

Adarsh Developers hasn't published one. When it does, it appears here exactly as published, with its dates. After its validity date it is struck through and leaves search and compare.

How much of it is ours to use?

Not published Not published

Ask Adarsh Developers for the carpet area of each plan. Ask Adarsh Developers

Where this comes fromNot published · ask Adarsh Developers

Adarsh Developers doesn't publish its plans with areas for this phase. Ask Adarsh Developers

Yours, and shared

Super built-up isn't published for these plans, so the share of it that is yours can't be worked out.

For comparison, Bengaluru's average loading (the share of the super built-up area outside your walls) was 41% in Q1 2025.

ANAROCK via Business Standard · secondary · 7 Oct

Floor bands

Not published. Builders publish floor bands, dated; we never infer them, and nobody here will tell you "only two left". Bands older than 14 days are hidden.

On the register: 307 of 309 booked, by the Q1 2026-27 quarterly report: a quarter behind. Source: K-RERA, as of 7 Oct 2026.

When do we get the keys?

In part K-RERA completion Jul 2029 · builder's date not published · K-RERA, 7 Oct 2026

K-RERA's proposed completion. Adarsh Developers doesn't publish its own date. Ask Adarsh Developers

Where this comes fromK-RERA · 7 OctNot published · ask Adarsh Developers
  1. Registered11 Oct 2022Read from the registration number, as printed by the promoter
  2. Today21 Oct 2026
  3. The builder's dateNot publishedOnly K-RERA's date is known
  4. K-RERA's completion dateJuly 2029Source: K-RERA, as of 7 Oct 2026

Time used against built

RegistrationBuiltTime goneBookedReport
PRM/KA/RERA/1251/446/PR/111022/00530998%89%307 of 309Q1 2026-27, filed 15 Jul 2026
PRM/KA/RERA/1251/446/PR/010325/00753513%37%289 of 694Q1 2026-27, filed 15 Jul 2026

Source: K-RERA, as of 7 Oct 2026. Built is the promoter's own figure in its quarterly report; time gone runs from approval to K-RERA's completion date. Never "selling fast".

Starting prices

PhaseFrom, before chargesPublishedKeys, builder's date
Adarsh Tropica – Phase IINot publishedNot publishedNot published

As published by the promoter, with the day we read it. First recorded on that day: the line starts there. No forecast, no estimate of value.

Is it on schedule?

Published 13% built, 37% of the time gone · K-RERA, 7 Oct 2026

behind time, by the promoter's own quarterly report, Q1 2026-27 (filed 15 Jul 2026).

Where this comes fromK-RERA · 7 Oct

Does this builder deliver on time?

Being compiled Being compiled · K-RERA, 7 Oct 2026

Promised against delivered, from K-RERA and occupancy certificates, by one method for every builder, with the builder's reply beside it. On the register so far: 30 registrations; of the 17 past their first completion date, 16 were extended. OC dates aren't read yet.

Where this comes fromK-RERA · 7 Oct

Adarsh Developers, the promoter of Adarsh Tropica – Phase II.

Registrations, Adarsh Tropica – Phase II

  • PRM/KA/RERA/1251/446/PR/111022/005309 Register check · 7 Oct
  • PRM/KA/RERA/1251/446/PR/010325/007535 Register check · 7 Oct

Look it up on K-RERA (opens rera.karnataka.gov.in in a new tab)

Delivery record

Being compiled. Promised against delivered, from K-RERA and occupancy certificates, by one method for every builder, with the builder's reply beside it. On the register so far: 30 registrations; of the 17 past their first completion date, 16 were extended. OC dates aren't read yet.

K-RERA · 7 Oct

Adarsh Developers’ reply: none yet. Every builder may reply to its record, dated, in its own words, shown beside it.

Money

No financier disclosure published.

Banks approved for buyers: not published.

Who to tell

  • About the homeAdarsh Developers
  • About the projectK-RERA, rera.karnataka.gov.in
  • About what we showedhello@clikin.ai

Something on this page wrong, or a builder's person unkind to you? Report it; Clikin.ai's grievance officer answers.

Is it registered, and can we read the papers?

In part Two K-RERA registrations · Register check, 7 Oct 2026

Numbers as printed by the promoter, each found on the register. K-RERA's pages hold the fire noc, height clearance, plan sanction, water source: listed below. Ask Adarsh Developers

Where this comes fromRegister check · 7 Oct
  • K-RERA registrationOn the register, checked 7 Oct 2026
  • Plan sanctionBDA - Bangalore Development Authority, BDA/NM/A.S/A.A-1/T.S-4/E-14/21-22, 30 Sep 2021 · K-RERA
  • Commencement certificateNot published · ask
  • Encumbrance certificateNot published · ask
  • Fire NOCApproved, applied 22 Nov 2018 · K-RERA
  • Height clearanceApproved, applied 23 Aug 2018 · K-RERA
  • Water sourceApproved, applied 22 Dec 2018 · K-RERA
  • Occupancy certificateNot due while it is being built

Missing a paper? Ask Adarsh Developers for it. Only public documents the builder has licensed are shown here.

Read the registration on K-RERA (opens rera.karnataka.gov.in in a new tab)

What is still available?

Not published Not published · K-RERA, 7 Oct 2026

Ask Adarsh Developers which floors are still open. The register's last quarterly report, Q1 2026-27, shows 307 of 309 booked, a quarter behind. Ask Adarsh Developers

Where this comes fromNot published · ask Adarsh DevelopersK-RERA · 7 Oct

Floor plans and floor bands are with the homes, under How much of it is ours to use?

How far is it from the places that matter to us?

In part Your places, on this phone

Add a place near your work or your parents' home for a straight-line distance; your places stay on this phone. Schools nearby aren't published by Adarsh Developers. Ask Adarsh Developers

Where this comes fromNot published · ask Adarsh Developers

How far is it from the places that matter to you?

From Adarsh Tropica – Phase II's published location (from the K-RERA register), as the crow flies: straight-line distances, not by road. The airport, tech parks and metro stations from OpenStreetMap, read 7 Oct 2026.

123456Adarsh Tropica – Phase II
Open in Google Maps (opens in a new tab)
  1. Tech parkRMZ Ecospace, Bellandurabout 4.4 kmstraight-line distance
  2. Metro stationBeratena Agraharaabout 4.6 kmstraight-line distance
  3. Metro stationElectronic Cityabout 4.6 kmstraight-line distance
  4. Metro stationHosa Roadabout 4.7 kmstraight-line distance
  5. Tech parkRMZ Ecoworld, Bellandurabout 4.9 kmstraight-line distance
  6. AirportKempegowda International Airportabout 35 kmstraight-line distance

Location: from the K-RERA register.

Add up to three places (an area or a metro station near your work or family) on My places; the straight-line distance from this project shows here. They stay on this phone. Peak-hour drive times come once a traffic source allows storing them.

Similar homes nearby

8 homes in Sarjapur Road and nearest to it, in a straight line. Ready first, then by price as published.

More from Adarsh Developers

14 other homes by Adarsh Developers on Clikin.ai. Ready first, then by price as published.

See all 15 homes by Adarsh Developers